‘This is a gem’: Contaminated greenspace in downtown Belleville to remain in municipal hands

A contaminated parcel of waterfront property in downtown Belleville will remain in public hands after city council quashed a proposed bylaw to declare the property surplus and give it away.
The fate of the greenspace at the corner of South John Street and Harbour Drive became a flashpoint of public and political debate in recent days.
The nearly one-acre site would be declared “non-viable” to municipal interests and transferred to a private third party based on receiving an unsolicited proposal, according to a City staff report.
“The abutting land owner contacted the city in 2023 as they advised they intended to build a
house on the abutting lot located at 41 South John Street, and inquired about acquiring the property from the City,” stated Diane McFarlane, the City’s Manager of Realty and Property Services.
McFarlane’s report also noted that municipalities are permitted to “allow the direct sale of land designated as ‘non-viable’ as a remnant parcel or contamination to an abutting landowner without public notice.”
Non-viable is defined as something that is not capable of living, growing, developing or functioning successfully.
However, on the notion of a waterfront land giveaway, councillors were having none of it.
They argued there is value to keeping the vacant property, adjacent to Jane Forrester Park, in public hands.
“This is a gem in the heart of our waterfront district and should be retained as such,” said Councillor Kelly Henderson.
The City originally acquired the South John Street lot, once home to fuel storage tanks, in 1973 for the token sum of $2, but left it vacant and undeveloped for over a half a century.
Disposing of a brownfield would remove a clean-up liability from the city’s books and could generate potential tax revenues, McFarlane’s report explained.


Aerial views of the property in question at South John Street and Harbour Drive. – Photos via Google and the City of Belleville
Council had already decided on March 23, 2026 to declare the property as surplus to municipal needs, but because the discussion took place in closed session it was never disclosed to the public at that time.
The first apparent inkling of political discontent occurred on April 13, 2026 when a bylaw to formally allow the public land transfer to private ownership, with no supporting information, was tabled in open session.
Councillor Kathryn Ann Brown requested that 2026-046: A By-Law to Declare Surplus and Convey to the Abutting Owner the municipal lands be paused for a follow up staff report.
Councillors cannot speak to a tabling motion, but the split 5-4 vote suggested growing discontent at the time.
Mayor Neil Ellis and Councillors Kathryn Ann Brown, Paul Carr, Barbara Enright-Miller and Margaret Seu voted in favour of tabling the bylaw.
Councillors Garnet Thompson, Lisa Anne Chatten, Kelly Henderson and Sean Kelly voted against tabling the bylaw.
When the subsequent staff report appeared on the Monday, May 11, 2026 council agenda, and as a more details emerged about the proposed land transfer, it appeared that most politicians were having second thoughts about proceeding.
Several voiced strong objections to transferring municipally-owned greenspace to another party at no cost, even if the land is contaminated.
Henderson told council she found it “insulting” that, as a taxpayer, the City would consider such an option.
“Giving away a prime piece of waterfront so that someone else can profit from it isn’t in the best interests of the taxpayers.”
Council heard that the owner of a neighbouring property sought to acquire the city-owned open space for the sole purpose of building a park at their own expense.
But critics, including several neighbourhood residents who gathered in the council chamber on May 11, said if a private owner could transform some of the unused land into a park, why couldn’t the City do the same?
The property isn’t considered a municipal park, but the open space is used as such by residents.
Brown said other municipal amenities could be developed to benefit residents in the future, such as multi-use sports courts, floral gardens and wayfinding signage for waterfront trail users.
“Why not keep it in City hands?” she said of the property, adding: “Once it’s gone, it’s gone.”
The City is not required to clean up the contaminated soil for passive park-related uses, she added.
Staff confirmed the City did not conduct a fair market real estate appraisal or conduct Phase 2 environmental testing to determine the extent of contamination prior to the site’s proposed disposal.
Still, Mayor Ellis agreed that it’s worth keeping the land in municipal ownership.
“If we do have to clean it up, it’s worth the value of cleaning it up because land (value) always goes up.”
Kelly pointed out that the same open space was identified four years ago as important in the City’s Parkland and Recreation Master Plan.
Carr described the way the process was handled, and the public backlash that resulted, as “unfortunate.”
He said the land surplus bylaw declaration was first introduced without much context and led to false suggestions in the community of a “backroom deal” in the works.
“The process here has been a little clumsy, and I’m not blaming staff individually or collectively, it’s just the context is lost and then unfortunately it grows legs.”
The bylaw declaring the South John Street land as surplus – clearing the way for the land transfer – was set to be voted on at the next council meeting in two weeks; but, given the overwhelming tone of the debate and growing community interest to maintain municipal ownership, councillors didn’t want to wait that long to quash it.
“I don’t want to waste two weeks on this” said Chatten.
Following a lengthy debate, councillors moved swiftly to undo the proposed bylaw.
In a procedural rarity, they voted in the two-thirds majority to advance the contentious bylaw to the floor at their May 11 meeting.
A motion to remove the surplus designation, and to have staff bring a future report on costing for development of the open space property, was carried by a unanimous 8-0 vote.
The public gallery of the council chambers burst into applause over the outcome.
The future report is also expected to identify risks on the property and the cost of remediation.
Thompson suggested the City may not have the funding at this time to transform the open space into park-related uses, but agreed the idea is worth exploring.
“Let’s look at this further.”
McFarlane’s report noted that retaining municipal ownership of a brownfield property means the continued assumption of all environmental risks, monitoring and potential future site clean-up.
While the exact cost of remediation of the South John Street property remains unknown, the report indicated the “average cost of this type of remediation begins at approximately $300,000 to $500,000.”

According to the CAO, during the last council meeting at which Bylaw 22026-046 was unanimously defeated, there would be no remediation costs to the City if the land remains as parkland and development is restricted to the surface only. IE: sports courts, trees, flower beds, paths etc.
The remediation estimates stated in the report would only apply if the site were redeveloped for structural improvement for residential or commercial construction.
The land has now been recognized as a valuable part of the City’s future waterfront recreational development and would likely remain as surface recreational use only.