MunicipalNewsQuinteist

Quinte West council votes 8-4 against proposed 12-month freeze on data centres

City of Quinte West municipal offices. – Photo by Emma Persaud

Editors note: Quinteist has corrected the spellings of councillors’ names in this story and apologizes for the error.

On Wednesday, Oct. 7. Quinte West council voted to defeat a motion to bring forward a 12-month interim control bylaw (ICBL) to freeze data centre construction.

The decision comes after a fiery Sept. 22 public meeting about introducing a zoning bylaw that would specifically accommodate data centre construction.

That meeting saw the Quinte council chambers packed to the brim and flowing over into the next room while dozens of people lined up to voice opposition toward a representative from TrueNorth Sustainable Infrastructure, who was attending to make the case for that company’s proposed micro data centre on Riverside Dr. in Trenton.

While the Oct. 7 meeting asaw another healthy turn out of concerned residents, the pro data-centre side was present than at the previous meeting held in June, were several delegates from private companies who have invested in data-related infrastructure in the area: First Block, a data centre company who also tries to recycle the heat energy produced from their infrastructure for sustainable uses, and Trinity Smart Farms, an agricultural technology company.

The representatives made the case to council that they should be exempt from a moratorium given their established investments in the area, and to make the case for the community benefits of proposed data centres.

The benefits they lined out would be in the following areas:

Capital investment and tax tevenue: The projects represent massive private capital investments—approximately $320 million for the Frankfurt Road project, and $380 million for the Riverside project. These developments would significantly increase the municipal tax base with no added burden on other public services,such as schools or hospitals.

Local economic activity: The construction phase of the Frankfurt Road project alone is estimated by the companies to generate over $64 million in local economic benefits, with an ongoing annual economic benefit of $12.25 million. First Block’s project also aims to bring up to $15 million in revenue to the electrical grid.

Construction and maintenance jobs: Each proposed facility is expected to create more than 100 construction jobs for local skilled tradespeople, as well as ongoing, long-term maintenance opportunities for local electricians and contractors.

High-paying permanent roles: The data centres would create permanent, highly sophisticated, and high-paying roles, such as Class 4 power engineers and computer science engineers.

Local sourcing commitment: Developers committed to a “concentric circle” sourcing model, looking first to the local community for all required materials, labour and jobs before expanding outward.

Circular energy and food production: Instead of wasting the thermal energy generated by the servers, the developers proposed capturing and reusing the heat. First Block proposed partnering with Trinity Smart Farms to use this recovered heat to power a vertical farming solution and external greenhouses, enabling year-round local food production and strengthening local supply chains.

Revitalizing properties: The projects would rejuvenate underutilized, long-empty industrial lands—such as the former Saputo factory and the old Sonoco paper mill—transforming them back into productive industrial parks without needing to cut down forests or develop greenfield spaces.

Donations to food banks: Trinity Smart Farms committed to dedicating one entire growing tower to Quinte West food banks, which would provide 300 to 2,000 heads of fresh produce (such as lettuce or broccoli) per week to local families in need year-round.

Educational retraining: True North offered to participate in and support job retraining programs through local schools, colleges and universities to help transition residents into technical roles.

Councillors Boyce, Card, Kuntze and Stedall were not swayed by the firms’ arguments and remained further in favour of a moratorium.

Their reasons included the following:

Need for a comprehensive planning policy: Supporters argued that the City needs time to complete a thorough review and establish a proper planning policy specifically tailored to data centers, rather than handling them piece-meal.

Unclear community benefits: Council members expressed concern that the proposed community benefits of these projects were not clear or legally guaranteed, and that the site plan process had occurred without public consultation or a final agreement outlining these benefits.

Waiting for provincial guidelines: There was a strong desire to wait for the Province of Ontario to finalize and implement its Bill 40 electricity playbook for data centres so the city could align its rules with provincial legislation.

Environmental and health concerns: Some councillors felt they did not yet understand the unique impacts of data centres—such as noise, health and safety risks, and the implications of “Class C” electricity designations—well enough to protect the community and environment.

Concerns over past due process: It was noted that a data centre had previously operated at the Sonoco site between 2023 and 2025 without obtaining a required site plan approval, raising trust issues regarding the property owner’s adherence to due process.

Opposition to exemptions: Supporters of the moratorium argued against exempting specific active projects (such as the Frankfurt Road/Sonoco project), stating that standardizing the rules for all future developments was necessary to avoid litigation and ensure a level playing field.

Councillors Armstrong, Kotsovos, McCue, O’Neil, Reid, Roseblade and Sharpe, who opposed the moratorium, or only supported it with exemptions for active applications, argued the following:

Unfairness of changing the rules mid-process: Opponents argued that developers had already spent significant time and money working in good faith through the City’s established regulations, permits, and environmental requirements. Changing the rules and freezing their projects at this stage was viewed as unfair.

Negative message to investors: Placing a blanket pause on developments was criticized as sending a negative message to outside businesses that Quinte West is not “open for business” or prepared to compete for future industries.

Loss of economic benefits: Opponents highlighted that blocking these projects would cost the community significant private capital investments, municipal tax revenues and local employment opportunities.

Trust in existing planning staff: Some councillors expressed full confidence in the city’s planning department and conservation authorities to address public concerns, noise limits and environmental protections through the standard site plan approval process without needing a freeze.

Risk of expiring power allocations: It was noted that the Frankfurt Road project had a fragile Hydro One capacity allocation set to expire in January 2027. Opponents warned that a lengthy moratorium would cause the developer to lose this power allocation, resulting in severe repercussions and the potential relocation of the project to another jurisdiction.

Preference for exempting active projects: Some council members were only willing to support a policy review if it exempted site plan proposals currently before the city, arguing that halting projects already in motion was a “dangerous practice.”

As for the concerns expressed by residents, opinions were slightly more mixed than at the previous meeting.
Jason Kish, a local business manager and Local 115 member spoke to the employment benefits for trades people date centre projects would bring.

“For trades people, construction is our livelihood,” said Kish.

“While data centres may not create a large number of permanent jobs once construction is complete, the construction of these facilities creates meaningful employment opportunities for our skilled trades people in this region.”

Kate Whitefield, a resident of Frankford expressed that the public simply needed more assurance that their livelihoods would be protected.

“I think the vast majority of residents just need to know that our health and environment will be protected from harmful operations,” said Whitfield

“We have trust issues because for years our environment and our health were impacted by harmful operations.”

Shantel Eddie of Trenton suggested the projects would ruin the town.

“I do not want a data centre here in Trenton on native land,” said Eddie. “I am 25 and I’ve lived here with my military family for 13 years, and I feel this is going to ruin our small town. They went through that whole process, one of these companies without coming to the public at all, and it feels like an extreme wrong.”

Derek Morgan, a major accounts manager at Business Development Bank of Canada, argued that Quinte West needs the productive investment that data represents.

“A vote to support moving this project forward is a vote for investment, jobs, assessment, growth, economic diversification and confidence in the future of Quinte West,” said Morgan.

“Conversely, rejecting or discouraging this opportunity sends a message to investors that Quinte West may not be prepared to compete for the industries that will drive tomorrow’s economy.”

Ultimately the council vote on imposing the 12-month moratorium was defeated 8 to 4.