Century-old Upper Bridge gets green light for major reconstruction, while Belleville explores removable gate system

Photo of the Front Street Upper Bridge via Google

One of downtown Belleville’s aging bridges over the Moira River is slated for a major face lift this year after city councillors approved a staff recommendation to keep using it for vehicles and pedestrians.

Council had earlier earmarked $4.1 million for extensive rehabilitation work on the century-old Front Street Upper Bridge, but held off on the work while staff explored whether it should be transformed into a pedestrian-only crossing.

At their Monday, March 9, 2026 meeting, councillors gave the major reconstruction project the green light after endorsing a Traffic Impact Study that concluded the best long-term use for the two-lane bridge should be for both vehicles and pedestrians.

However, Councillor Garnet Thompson asked City staff to report back on the cost of installing fixed gates on both sides the bridge, possibly the kind that can slide into place, so the bridge can easily be closed-off to vehicles when special events are held downtown.

Joseph Reid, the City’s Director of Transportation and Operations, said it costs between $3,000 and $5,000 to install portable barriers every time a downtown street is closed for a special event.

Installing a gate system on the Upper Bridge may be more expensive, but Thompson said it would likely pay for itself over time.

“If they close (downtown streets) three or four times a year that’s (a cost of) $10,000 to $15,000. So the gate may be $10,000 but it might be the best deal we ever get.”

Deanna O’Leary, the City’s manager of engineering, said the cost of installing gates isn’t part of the original bridge repair budget but promised to investigate the idea.

“We can look at that. It’s not included as part of the current rehabilitation. I think what we would do is come up with a plan for a gate or, however we want to close the bridge off, and bring that back for council consideration on the cost.”

The 65-metre long Upper Bridge, located just south of the Sagonaska Bridge, dates back to 1930 with heritage-style features such as a concrete bowstring arch structure.

It’s a busy downtown transportation route for motorists, cyclists and pedestrians with key connections including Station Street and Moira Street.

The planned rehabilitation work includes removal and reconstruction of cantilevered sidewalks and curbs, replacing the expansion joints, ballast walls, lighting and wiring, and waterproofing and paving the bridge deck.

Staff indicated they will issue the bridge construction tender right away.

In a March 10, 2026 news release, one day after Council’s decision, the City of Belleville further specified that construction is expected to begin this spring with the work completed by the fall of 2026.

“Construction will result in temporary traffic impacts in the surrounding area. The bridge and the section of the Parrott Riverfront Trail below the bridge will be close for the duration of construction,” the City stated.

Lane restrictions and short-term closures may be required on adjacent streets, and detours will be clearly marked, the statement noted.

In anticipation of losing the crossing to several months of construction work, the City will hold a public information session next week to provide project details, anticipated closure timelines and information on what to expect during the season-long construction period.

The session will take place Thursday, March 19 from 2 to 4 p.m. and 6 to 8 p.m. in the SMB Room at Belleville City Hall.

The Upper Bridge is one of six crossings used by vehicles over the Moira River between the city’s waterfront and Highway 401.